Wicstun Veterinary Group Hospital
EYG Commercial were selected to complete all glazing on this newbuild facility in East Yorkshire.
Our teams were amongst the first contractors on site in December 2019 at which point we completed the installation of all windows.
We returned to site in March 2020 to complete the installation of all external doors, including a high-specification main automatic entrance door which included significant steelwork and design input from the EYG team.
The team returned to site in July 2020 to complete the final aspects of the job and handover to the client, ready for opening in August.